36 Bannick Court
Canning Vale WA, 6155

Transpower New Zealand

Global Testing Services were engaged to test and commission the new Siemens HVDC equipment to Transpower specifications.

HVDC Inter-Island Link Pole 3 Benmore Substation

  • Client: Transpower New Zealand
  • Project Title: HVDC Inter-Island Link Pole 3 Benmore Substation
  • Commencement date: January 2011
  • Completion date: May 2013
  • Project Value: $672 Million

Scope

The HVDC link was first commissioned in April 1965 to primarily transport electricity from the generation-rich South Island to the more populous North Island. The link was originally a bipolar 600 MW link with mercury arc valves. The original equipment was paralleled onto a single pole (Pole 1) in 1992 and a new thyristor-based pole (Pole 2) was commissioned alongside it. This increased the link capacity to 1040 MW. Pole 1 was fully decommissioned effective 1 August 2012, and the replacement thyristor-based Pole 3 was fully commissioned on 29 May 2013, restoring the link to a bipolar 1200 MW configuration.

Global Testing Services were engaged to test and commission the new Siemens HVDC equipment to Transpower specifications.

Project Challenges

Sub zero temperatures during construction required innovative methods to minimise the effects.  Interaction with existing DC link substation required close coordination to minimise outages.

Case Study

This project replaced the existing Pole 1 with the new Pole 3 at Benmore Substation, comprising of state‐of‐the‐art thyristor valve converter equipment. It increased capacity of the high voltage direct current (HVDC) inter‐island link that connects Haywards substation in the North Island and Benmore substation in the South Island.

Construction consisted of the installation of equipment within the 220 kV switchyards and a new HVDC Convertor Station. This involved 220kV bus extension by string bus over the tail race between two switchyards, 3 new 80MVAr filter banks, four single phase 271MVA converter transformers, installation of 17 tonnes thyristor stacks suspended from the ceiling of the 19m high valve hall, HVDC switchyard including 34 tonne smoothing reactor, new control systems (inc. 102 new control and protection panels), 11 kV switchgear, AC and DC auxiliary supply for Pole 3 and complete replacement of 110V DC battery banks at Pole 2.

Cable installation and termination was a large part of the work with over 129,000 metres of cable run. Earthing of all new equipment and buildings also took place.

GTS working under contract to Electrix were among 60 contractors on site working in extreme ranges of temperature from ‐10 degrees Celsius in winter up to 40 degrees Celsius in the height of summer. This involved coming up with unique ideas to enable works to be carried out including heating cables and weather shelters. Meeting commissioning schedules required many tests to be carried out in these conditions.

Accreditations & Policies


 


Global Testing Services


Our team members travel all over Australia and the world, going to countries such as Malaysia, India, Vietnam, Egypt and throughout the Asia Pacific.

We take great pleasure in ensuring our clients get the specialised service they have come to expect from Global Testing Services.




 

Head Office
Perth
36 Bannick Court Canning Vale
WA 6155
Australia
 
Phone
+61 (08) 9456 7700
After hours
+61 400 040 010
Transformer Branch
Bunbury
21 Gibbons Road Davenport 
WA 6230
Australia
 
Phone
+61 (08) 9725 4583
After hours
+61 428 648 848
Pilbara Branch
Newman
Equal Certification does not cover our Newman operation
1/85 Welsh Drive
Newman
WA 6753
Australia
 
Phone
+61 (08) 9175 0177
After hours
+61 437 043 433

Request a call back

If you’d like to find out more about our services, or how we can work with you, please fill in the Request a Call Back and one of our team will get back to you within 24 hours.

COPYRIGHT © Global Testing Services 2024. 
All Rights Reserved

Site by: Hyperactive Digital